Areguling Hills

Villa Boutique Hillside Sanctuary. Ten private-pool villas on three stone terraces above the bay.

Concept phase · Draft v1 · 5 Oct 2026

Architectural notice

A row of open pavilions facing the bay, with the view as the centre of the plan.

Ten villas, six Single Bedroom (100 m²) and four Double Bedroom (160 m²), are spread over three stone terraces on a 60-are site. Each stands on an andesite platform, with a light timber frame and sliding glass walls that open fully to the pool and the sea.

A two-tier thatched roof shelters the living space. The upper tier is a louvred clerestory that lets hot air out and filters the light; the eaves project 1 m beyond the posts against sun and rain.

Shared facilities, namely reception, restaurant, pool club, spa and a sunset gazebo with fire pit, are grouped near the entrance and at the crest, so the slope between stays lush and quiet.

Site
6,000 m² (60 are)
Location
Jl. Wisata Areguling, Lombok Tengah
Villas
6 Single + 4 Double
Private pools
310 m²
Roofed area
1,950 m² (32.5%)
Green / planted slope
1,690 m² (28.2%)
Programme
≈ 24 months
Double bedroom villa at sunset

One architecture, repeated ten times

Three gestures, in local materials that age well.

Stone terrace

An andesite platform 45 cm high and retaining walls form level terraces on the slope and control erosion.

Light frame

Timber posts and beams with sliding glass walls give a living volume open on every side.

Great roof

A two-tier thatched roof with a louvred clerestory brings light and air movement to the centre of the villa.

Single bedroom villaLiving room open to the pool terraceThatch, teak slats, volcanic stone and woven textile

Two villa types

Single Bedroom · 100 m²

6 units · deck 30 m² · pool 5 × 5 m

Ground floor plan, single bedroom villa
Spacem²
Living + dining28.0
Pantry6.0
Entry / corridor8.2
Master bedroom23.9
WIC5.1
Bathroom13.8
Veranda15.0
Total100.0

Double Bedroom · 160 m²

4 units · deck about 50 m² · pool 4 × 10 m

Ground floor plan, double bedroom villa
Spacem²
Master bedroom25.0
Bedroom 222.5
Living + dining39.0
Kitchen6.8
Entry6.8
Master bathroom11.2
Bathroom 210.0
Master WIC7.5
Storage / WIC 211.2
Veranda20.0
Total160.0

Concept drawings. Dimensions are schematic and must be verified by a licensed architect and structural engineer.

Masterplan

Three terraces, ten villas, and an arrival zone beside the road.

TerraceContents
ArrivalGate, parking for 12 cars, lobby + restaurant 300 m², staff area 200 m²
1S1–S3, D1 · pool club 120 m², spa 100 m²
2D2, D3, S4, S5 · stone stairs and buggy path
3 (crest)D4, S6 · sunset gazebo with fire pit, main water tank

Land use

Usem²%
Roofed buildings1,95032.5
Pools and decks96016.0
Roads, parking, paths1,40023.3
Green and planted slopes1,69028.2
Total6,000100
Schematic masterplan with three terraces
Schematic masterplan, 1:400. Final positions depend on the topographic survey.
Arrival pavilion with restaurant and the villas above

The site, honestly described

A 60-are hillside beside Jl. Wisata Areguling, with views over the bay, rice terraces and coconut palms.

Site boundary on satellite map
Site boundary (indicative; to be re-surveyed)
Panorama from the plot to the bay and rice valley
Panorama to the bay and rice valley
Aerial photo of the slope and access road
Aerial view of the slope and access road

Strengths

Open views of the bay, rice fields and coconut groves · natural contours suited to terracing · road access and nearby village for labour and power · villa development already under way on the opposite hill.

What we are checking

Ground cracks and erosion channels on the open slope (geotechnical survey required) · sparse vegetation and rainy-season risk, roughly Nov–Mar · irregular plot shape to re-measure · limited fresh water, so borehole or tanker supply plus rainwater storage · nearby stockpile/quarry activity (dust, noise).

Climate, comfort and infrastructure

Shade by design

Eaves project 1.0 m from the posts. At December noon the sun stands at about 75° and the view-side glazing is fully shaded; in June it passes to the north at about 58°.

Air that moves

A 0.80 m louvred clerestory releases hot air at the highest point; sliding glass on the view side and windows on the hill side open a cross-flow. Natural ventilation is the intent; thermal comfort is yet to be measured.

Water, power, safety

Gravity-fed water from a tank on the crest, biological wastewater treatment at the lowest point, 60–100 kWp of solar, rainwater infiltration, fire detection and a 3.5–4 m fire-truck access.

Master bedroom opening to the pool deckStone bathtub and garden bathroomPool club and restaurant at dusk

Costs and planning projection

A realistic hospitality yield, not a promise of extraordinary returns. Land value is excluded.

Cost, Rp millionRp M%
Villas (A): buildings, pools, decks17,45033.7
Shared facilities (B)7,03513.6
Site works (C)7,98015.4
Utilities and systems (D)4,1508.0
Landscape (E)1,5002.9
Construction subtotal38,11573.7
Contingency 10%3,8127.4
Design, survey, PM, legal3,7097.2
FF&E and equipment4,9009.5
Pre-opening and launch1,2002.3
TOTAL (excl. land)51,736100
Stable year projectionValue
ADR Single / DoubleRp 3.8 / 6.0 M
Stable occupancy65%
Room revenueRp 11.1 bn
F&B, spa, other (25%)Rp 2.8 bn
Total revenueRp 13.9 bn
GOP 42%Rp 5.8 bn
NOIRp 4.9 bn
Yield on cost9.4%
10-year IRR incl. resale value≈ 9–10%

Alternative: a leasehold/strata sale scheme with gross sales of about Rp 74 billion and a pre-land profit of about Rp 14.9 billion, or a hybrid (sell 4 Double, operate 6 Single). Figures are not yet validated by contractors or a market consultant. Rp 51.7 billion is about US$3.1 million at Rp 16,500/US$.

Due diligence roadmap

The order we follow: legal status of the land and zoning first, then lock the detailed design. Permits are the largest schedule risk after the geotechnical survey.

ItemAuthorityStatus
Land title (SHM/HGB), boundaries, setbacks, disputesLand office, notary/PPATNot started
Company (PT / PT PMA), NIB/OSS, accommodation KBLINotary, OSSNot started
KKPR and RDTR/RTRW compliance (coverage, green ratio, setbacks, height)Public works / one-stop serviceNot started
Environmental document (SPPL / UKL-UPL / AMDAL), groundwater permitEnvironment agencyNot started
Building permit (PBG), occupancy certificate (SLF)Public works / one-stop serviceNot started
Tourism business registration (TDUP), CHSETourism officeNot started
Foreign-investor structure: Hak Pakai, lease, or PT PMA with HGBNotary, legal counselNot started
Village agreement, road access, local employmentVillage governmentNot started

Schedule and phasing

About 24 months in total. Earthworks fall in the dry season, roughly April to October.

Topographic and geotechnical survey
Concept to detailed design (DED)
Permits (KKPR, PBG, environment)
Contractor selection
Earthworks, terracing, drainage
Access, main utilities, wastewater plant
Phase 1: lobby, pool club, S1–S3, D1, D2
Phase 2: S4–S6, D3, D4, spa, gazebo
Furnishing, staff training, trial stays
Soft opening / grand opening
06121824 months

Interested in Areguling Hills?

Request the full dossier with plans, cost breakdown and permit roadmap, or book a call with the team.